The project kicked off on August 6th with demolition of existing sidewalks on the north side of W Tidwell beginning at the bridge over White Oak Bayou. The crew worked toward Deep Forest Drive.
The crew has continued working toward Antoine Drive, with new concrete pours following the demolition and form setting.
The schedule for the weeks of August 25 – September 8:
- Pouring concrete from Deep Creek to Ash Oak
- Final grading and sodding from Deep Creek to Ash Oak
- New pavement lane markings on bridge over White Oak Bayou
- Widening of sidewalks on White Oak Bayou bridge
Note: weather may impact the schedule.