W Tidwell Project Updates – Sept 19, 2024

Our project signs have been installed at both ends of the project.

The construction crew has demo’d from the White Oak Bayou bridge to Ash Creek and poured new sidewalks.  They will be pouring the colored bands and corner ramps at Deep Creek next week.

The lane striping across White Oak Bayou has been shifted toward the center.  This will give space for widening the sidewalks on the bridge.  That work is currently underway.

The schedule for the weeks of September 23 – October 6:

  • Pour corner ramps and colored bands at Deep Creek
  • Pour sidewalk extensions on White Oak Bayou bridge, both sides
  • Demolition of sidewalks on south side from west of Bolivia to White Oak Bayou bridge
  • Pour new sidewalks on south side of from west of Bolivia to White Oak Bayou bridge

Note: weather may impact the schedule.